Registration/Renewal Granted Dashbaord

 
( Results between 01-04-2020 and 23-07-2021 )  
     
     

Factory Act License

Sr. No. Title Total
1 Time Limit prescribed as per the Public Service Guarantee Act 45 days
2 Total Number of applications received 2206
3 Total Number of applications approved 1183
4 Total Number of applications Rejected 965
5 Total Number of applications Pending 65
6 Average time taken to obtain registration/renewal 24 days
7 Median time taken to obtain registration/renewal 24 days
8 Minimum time taken to obtain registration/renewal 1 days
9 Maximum time taken to obtain registration/renewal 72 days

Shops & Comm. Estt

Sr. No. Title Total
1 Time Limit prescribed as per the Public Service Guarantee Act 1 day
2 Total Number of applications received 39961
3 Total Number of applications approved 23007
4 Total Number of applications Rejected 15919
5 Total Number of applications Pending 1035
6 Average time taken to obtain registration/renewal 6 days
7 Median time taken to obtain registration/renewal 4 days
8 Minimum time taken to obtain registration/renewal 1 days
9 Maximum time taken to obtain registration/renewal 153 days

BOCW Establishment Registration License

Sr. No. Title Total
1 Time Limit prescribed as per the Public Service Guarantee Act 30 days
2 Total Number of applications received 670
3 Total Number of applications approved 424
4 Total Number of applications Rejected 180
5 Total Number of applications Pending 66
6 Average time taken to obtain registration/renewal 23 days
7 Median time taken to obtain registration/renewal 22 days
8 Minimum time taken to obtain registration/renewal 1 days
9 Maximum time taken to obtain registration/renewal 65 days

Factory Building Plan

Sr. No. Title Total
1 Time Limit prescribed as per the Public Service Guarantee Act 45 days
2 Total Number of applications received 1855
3 Total Number of applications approved 1399
4 Total Number of applications Rejected 313
5 Total Number of applications Pending 143
6 Average time taken to obtain registration/renewal 25 days
7 Median time taken to obtain registration/renewal 25 days
8 Minimum time taken to obtain registration/renewal 1 days
9 Maximum time taken to obtain registration/renewal 68 days

RC Contract License

Sr. No. Title Total
1 Time Limit prescribed as per the Public Service Guarantee Act 26 days
2 Total Number of applications received 267
3 Total Number of applications approved 178
4 Total Number of applications Rejected 71
5 Total Number of applications Pending 18
6 Average time taken to obtain registration/renewal 21 days
7 Median time taken to obtain registration/renewal 21 days
8 Minimum time taken to obtain registration/renewal 1 days
9 Maximum time taken to obtain registration/renewal 55 days

Contractor Labour License

Sr. No. Title Total
1 Time Limit prescribed as per the Public Service Guarantee Act 26 days
2 Total Number of applications received 3715
3 Total Number of applications approved 3345
4 Total Number of applications Rejected 320
5 Total Number of applications Pending 49
6 Average time taken to obtain registration/renewal 9 days
7 Median time taken to obtain registration/renewal 4 days
8 Minimum time taken to obtain registration/renewal 11 days
9 Maximum time taken to obtain registration/renewal 11 days

Interstate Contractor License

Sr. No. Title Total
1 Time Limit prescribed as per the Public Service Guarantee Act 26 days
2 Total Number of applications received 26
3 Total Number of applications approved 14
4 Total Number of applications Rejected 8
5 Total Number of applications Pending 4
6 Average time taken to obtain registration/renewal 65 days
7 Median time taken to obtain registration/renewal 56.5 days
8 Minimum time taken to obtain registration/renewal 20 days
9 Maximum time taken to obtain registration/renewal 145 days